Halfmoon Bay Community Hall Construction Underway

Tags:  2025 | News Release
Date Released: June 30, 2025

Construction kicked off in April for the Halfmoon Bay Community Hall Located in Connor Park / ch’emalaḵ. Since then, significant progress has been made with on-site preparation and initial construction.

Key milestones over the past two months include:

  • The septic disposal field has been upgraded. This follows earlier utility work that included septic upgrades for the hall.
  • A new water service has been installed.
  • A new fire hydrant has been installed.
  • A new power pole has been installed. This is part of the electrical connection utility work for the hall.
  • The footings have been poured, and foundation walls have been formed.

 

Additionally, an older shed structure on the southwest side of the site, previously used as a washroom, has been dismantled, and the pit toilet has been fully decommissioned. This was done in a manner to ensure trees bordering the existing pit were not disrupted.

This project, which is largely funded through the Investing in Canada Infrastructure Program, is moving forward on-time with the hall due to be available for the community by Summer 2026.

As work continues, visitors to Connor Park may see temporary changes to parking availability.

Stay connected and follow the hall’s progress on our online information hub at letstalk.scrd.ca/community-hall.

Ask questions anytime and watch as the hall takes shape!